250 Ton Transformer on the Move

Over Memorial Day weekend Flanigan crews assisted Hake Rigging with the unloading of three very large transformers from a barge at Vulcan Stone quarry in Havre de Grace, MD. Crews had to manage the half-million pound transformers around the shifting tides and had to take significant measures counter-weighting the barge so that the load could be rolled-off smoothly. The following week Flanigan provided emergency repair assistance to the Hake crews during the 5 MPH crawl to the energy plant in Peach Bottom, PA.